![]() Task 2 is just a dummy task to factor in the necessary drying phase for the paint. Task 3: Complete interior setup and furnishing (5 days, Monday – Friday) Task 2: Drying phase (2 days, schedule for Saturday & Sunday) Task 1: Paint interior of house (3 days, finishes on Friday) Here’s how to achieve the desired exception for one task. ![]() (Note: In this context, you may also want to add overtime with special weekend rates). All we want to do is have a specific task continue on weekends. The thing is we don’t want to change the overall project calendar. ![]()